Courtyard Elevations.
Pictures taken from R1 Level from gridline 7 and F.9 facing north to south: Phase 1 has been poured.
Photo from D-5.5 corner on podium deck level facing north to west to south to east: shown rebars are near completion; cans, sleeves, conduits, etc are in place.
Shotcrete wall is done on East wall (all shotcrete walls are finished)
Shoring for Phase 1 podium deck is in progress; shoring is being erected and formed.
Columns have been poured. Column forms are being removed as shown in the picture.
Shows street level slab poured (phase 1), verticals (columns, walls) are starting; reinforcement is being placed.
Shoring has been installed for the first pour and top and bottom rebars are being placed.
Shows that the CMU walls are on the second lift for grouting, shoring has started to be installed on the north side of the property for the ground floor slab, the elevator pit has be dug and the sh...
Pictures show column from grid 1 to 6 have been poured. Block walls on axis 1+D to 6+D has been grouted as well. Block walls are being set again for next lift.
shown are column pads have been previously poured and currently the rebars for the columns are being placed. Also, the wall foundation is being poured for phase 1 (north side of east wall, north wa...
Pictures show that the column pads for phase 1 is ready and has passed inspection. Pouring of concrete will start on Monday. Also, shown is the wall foundation being prepared. Waterproofing membran...